Due to the rainy weather on October 30 and 31, the lane closure schedule for the work to widen Collier Road has shifted. There will be a single lane of Collier Road closed from 9 a.m. – 4 p.m. on the following days:

  • Friday, Nov. 1 – Saturday, Nov. 2 – Piedmont’s contractor will replace the soil and binder at the metal plate that City of Atlanta removed on Tuesday, 10/29, as well as install light poles.
  • Saturday, Nov. 2 – Sunday, Nov. 3 – Georgia Power will be performing work on the utility poles.
  • Monday, Nov. 4 – Friday, Nov. 8 – Piedmont’s contractor will mill and pave Collier Road.

Additionally, AT&T and Comcast are doing work on the utility poles along Collier Road between Monday, Oct. 28 – Friday, Nov. 1, and outages may be experienced during this work.​