Building Update for Piedmont Atlanta Tower: Week of Feb. 18 – 24

Hauling dirt from Hospital North: Dirt mounds will be removed and hauled by large trucks. Entry and exit points will be created separately for the trucks to ensure minimal traffic and disruption to the patient and Ambulance Entrance on Peachtree Road. This work is expected to last three weeks.

Metal sheets on Collier Road: We are exploring underground utilities along Collier Road to minimize the risk of outages during the construction process. In order to do this, we have to cut across the road, explore the site and cover the lane with metal sheets while the asphalt is lifted. After each lane is explored, the road will be repaved, and we will move into the next lane. We expect to have this work completed by the end of next week. Lane closure permits and other necessary approvals were obtained from the city.