Building Update for Piedmont Atlanta Tower: Week of March 17-24

Rock Blasting: Rock blasting will occur every day at 2:15 p.m. for the next three weeks. This is a standard process to remove underground rock from the construction site. We expect minimal impact on the surrounding neighborhood but will continue to monitor vibration levels.

Facility entrance changes, lane striping: In anticipation of lane and entrance closures around the hospital throughout the duration of construction, we will be restriping roads that run through the campus to accommodate traffic. We will be enforcing parking restrictions during this time ensure vehicles are not blocking passage at any point. Please be mindful of signage as you visit the hospital.