Drilling Materials: Drilling continues this week near the East Tower and the former 1-Center area. Minimal impact is expected on the hospital and the surrounding area, but there will be additional drilling equipment inside the construction site.

Rock Blasting: Rock blasting continues this week in the fenced-off construction area. Blasting will take place every day at 2:15 p.m.

Major Site Excavation: Site excavation and dirt dumping are underway this week near hospital north. Trucks will exit onto Peachtree Road throughout the day and may cause brief intermittent traffic. Trucks are thoroughly cleaned before exiting the construction site to ensure they do not compromise safety of patients, visitors or general traffic.

Sidewalk/Roadwork on Peachtree: Road construction along Peachtree is a separate project being conducted by a third party organization and is not affiliated with the Piedmont Atlanta Tower. Please be mindful of signage indicating sidewalk and lane closures.

Loading Dock Vault: Crews are expected to complete work on the tower loading dock vault, another major milestone in construction, next week.