1-Center Demolition: Full-scale demolition (using large, noisy demolition equipment) of 1-Center continues this week and is expected to last through the end of June.

Please note that we are not using explosives or blasting to demolish 1-Center; crews are using a claw similar to the one used in the Sheffield Building demolition to demolish the building piece-by-piece.

Lane Closures on Peachtree Road: Due to city-related bridge construction on Peachtree Road, this project, originally slated to start the week of June 5, was postponed and will now occur over the next two weekends: June 10 -11 and June 17 -18.

Trucks Exiting onto Collier: Throughout this summer, we will periodically route construction vehicles through Collier Road to accommodate GDOT construction projects on Peachtree Road. Construction vehicles will use Collier Road, an approved haul route, and will not use any of the neighborhood roads.​

Rock Blasting: Rock blasting continues this week in the fenced-off construction area. Blasting will take place every day at 2:15 p.m.

Additional Trailers, Hospital North: Crews will need to close Ambulance Drive the weekend of June 10-11 in order to install additional construction trailers. Signage will be posted directing traffic to alternate entrances, and leadership is working with EMS to provide advance notice.