Project Status: The concrete frame of the Piedmont Atlanta Tower has now risen above Peachtree Road. Level 1 concrete will be 90% complete before the end of March. To date, approximately 35% of all concrete is complete. Tomorrow, crews will pour concrete for what will eventually be the lobby area of the building.