Building Update for Piedmont Atlanta Tower: Week of October 6-13

Potholing Across Collier Road: As we prepare for a water line installation across Collier Road, crews will hydrovac under the road, a process that will better ensure services such as electricity, gas and other underground utilities are not damaged or disrupted. This work will require closure of two lanes near 2 Collier Road from 9 a.m. to 7 p.m. on Saturday, October 21 through Monday, October 23. Excavation sites will be covered with metal plates between hours of operation.

Work will be concentrated over the weekend to mitigate traffic and the length of time the plates will be on the road. No loss of water will be experienced to neighboring properties during this time.

Traffic Around Construction Site: Trucks continue to enter and exit the construction site on Collier and/or Peachtree Roads. This may lead to brief, intermittent increases in traffic throughout the day.