Building Update for Piedmont Atlanta Tower: Week of September 1-8

Peachtree Road Lane Closings: Water line installation will now take place over a 6-day period from Thursday, September 7 through Tuesday, September 12. Work will involve closure of up to two lanes at a time on Peachtree Road. All work will be completed during the day, and certified flagmen will be posted to direct traffic. We appreciate your patience during this construction.

Tower Cranes: Tower cranes are currently being erected in the fenced-off construction area. All three cranes will be erected by the middle of September.

Major Site Excavation: Site excavation continues this week. Trucks may cause brief intermittent traffic. Any loose dirt is removed from the trucks before exiting the construction site to ensure they do not compromise safety of patients, visitors or general traffic. 

2021-01-25T20:23:21+00:00