  • April 6

Building Update for Piedmont Atlanta Tower: April 6

April 9, 2018

Collier Road Work: Crews are currently conducting roadwork on Collier Road. The Piedmont Atlanta Tower team is not leading this project and therefore cannot dictate...
  • March 9-16

Building Update for Piedmont Atlanta Tower: Week of March 9-16

March 9, 2018

Project Status: The concrete frame of the Piedmont Atlanta Tower has now risen above Peachtree Road. Level 1 concrete will be 90% complete before the end...
  • February 16-23

Building Update for Piedmont Atlanta Tower: Week of February 16-23

February 19, 2018

Project Status: Crews are currently on the second level of the building. This floor will house the tower’s Invasive Cardiovascular Services Center, which will include...
  • February 9-16

Building Update for Piedmont Atlanta Tower: Week of February 9-16

February 11, 2018

Utility Work Along Collier Road: Georgia Power continues work this week installing a new manhole near the entrance to the Piedmont Atlanta Hospital loading dock...
  • February 2-9

Building Update for Piedmont Atlanta Tower: Week of February 2-9

February 2, 2018

Utility Work Along Collier Road: Georgia Power continues work this week installing a new manhole near the entrance to the Piedmont Atlanta Hospital loading dock...
  • Building update for January 26 - February 2

Building Update for Piedmont Atlanta Tower: Week of January 26- February 2

January 29, 2018

Project Status: Despite challenging weather conditions from the past year (snowstorms, record low temperatures and hurricanes) the Piedmont Atlanta Tower construction is currently on track...
  • Building update for January 19-26

Building Update for Piedmont Atlanta Tower: Week of January 19-26

January 20, 2018

Utility Work Along Collier Road: Georgia Power began roadwork earlier this week installing a new manhole near the entrance to the Piedmont Atlanta Hospital loading...
  • Building update for January 5-12

Building Update for Piedmont Atlanta Tower: Week of January 5-12

January 8, 2018

Georgia Power working in Collier Road: Please be advised that Georgia Power will conduct roadwork installing a new manhole near the entrance to the Piedmont...

Building Update for Piedmont Atlanta Tower: Week of December 22-29

December 22, 2017

REMINDER Site Closure: The construction site will be closed from Saturday, December 23, to Monday, December 25. Construction will resume Tuesday, December 26.  

Building Update for Piedmont Atlanta Tower: Week of December 15-22

December 15, 2017

Site Closure: The construction site will be closed from Saturday, December 23, to Monday, December 25. Construction will resume Tuesday, December 26. Concrete pours: To...
  • Building update for December 8-15

Building Update for Piedmont Atlanta Tower: Week of December 8-15

December 8, 2017

Elevated Structure: Work on the elevated structure of the building continues this week, providing an initial glimpse into the full size and shape of the...
  • Building update for November 17-24

Building Update for Piedmont Atlanta Tower: Week of December 1-8

December 4, 2017

Slab Pours: Progress continues on the initial outline shape of the Piedmont Atlanta Tower, as we poured our first elevated slab this week, which will...
  • Building update for November 17-24

Building Update for Piedmont Atlanta Tower: Week of November 17-24

November 18, 2017

First Slab Pours: Progress continues on the initial outline shape of the Piedmont Atlanta Tower, as we poured our first elevated slab this week, which...
  • Building update for November 10-17

Building Update for Piedmont Atlanta Tower: Week of November 10-17

November 13, 2017

Structure Footings: We have reached several major milestones in construction of the Piedmont Atlanta Hospital Tower, most recently the basement level footings of the structure,...
  • Building Update for Piedmont Atlanta Tower: Week of November 3-10

Building Update for Piedmont Atlanta Tower: Week of November 3-10

November 3, 2017

Collier Road Work: In conjunction with a plan developed with the city of Atlanta, work will take place to install a water line under Collier...
  • Building Update for Piedmont Atlanta Tower: Week of November 3-10

Building Update for Piedmont Atlanta Tower: Week of October 27 – November 3

October 28, 2017

Collier Road Work: In conjunction with a plan developed with the city of Atlanta, work will take place to install a water line under Collier...
  • Building Update for Piedmont Atlanta Tower: Week of October 20-27

Building Update for Piedmont Atlanta Tower: Week of October 20-27

October 20, 2017

Hydrovacing Across Collier Road: In preparation of a water line installation, crews will be hydrovacing under Collier Road, a process that will better prevent damage...
  • Progress from October 13-20

Building Update for Piedmont Atlanta Tower: Week of October 13-20

October 16, 2017

Potholing Across Collier Road: A water line will be installed across Collier Road, near the front areas of the buildings located at 2 Collier Road...
  • The foundation is currently being constructed at the new Piedmont Medical Building

Building Update for Piedmont Atlanta Tower: Week of October 6-13

October 6, 2017

Potholing Across Collier Road: As we prepare for a water line installation across Collier Road, crews will hydrovac under the road, a process that will...

Building Update for Piedmont Atlanta Tower: Week of September 29 – October 6

September 29, 2017

September 29-October 6 First slabs: We reached a major milestone in construction as we poured the first concrete slabs of what will be the very...

Building Update for Piedmont Atlanta Tower: Week of September 22-29

September 22, 2017

September 22-29 Peachtree Road Lane Closings: This project is currently underway to connect underground utilities across Peachtree Road. Overnight work (9 p.m. to 4:30 a.m.) will...

Building Update for Piedmont Atlanta Tower: Week of September 15-22

September 15, 2017

Peachtree Road Lane Closings: Due to constraints presented by Tropical Storm Irma, construction on Peachtree Road has been postponed. This work will now take place...

Building Update for Piedmont Atlanta Tower: Week of September 8-15

September 8, 2017

Peachtree Road Lane Closings: Due to constraints presented by Hurricane Irma, construction on Peachtree Road has been postponed until Wednesday, September 13. Hurricane Irma: As...
  • The Pit as of September 1, 2017

Building Update for Piedmont Atlanta Tower: Week of September 1-8

September 5, 2017

Peachtree Road Lane Closings: Water line installation will now take place over a 6-day period from Thursday, September 7 through Tuesday, September 12. Work will...
  • Major Site Excavation

Building Update for Piedmont Atlanta Tower: Week of August 25 – September 1

August 25, 2017

Peachtree Road Lane Closings: To coordinate with other activities and roadwork planned on Peachtree Road, there has been a change to the schedule for the...