  • Building update for December 8-15

Building Update for Piedmont Atlanta Tower: Week of December 8-15

December 8, 2017

Elevated Structure: Work on the elevated structure of the building continues this week, providing an initial glimpse into the full size and shape of the...
  • Building update for November 17-24

Building Update for Piedmont Atlanta Tower: Week of December 1-8

December 4, 2017

Slab Pours: Progress continues on the initial outline shape of the Piedmont Atlanta Tower, as we poured our first elevated slab this week, which will...
  • Building update for November 17-24

Building Update for Piedmont Atlanta Tower: Week of November 17-24

November 18, 2017

First Slab Pours: Progress continues on the initial outline shape of the Piedmont Atlanta Tower, as we poured our first elevated slab this week, which...
  • Building update for November 10-17

Building Update for Piedmont Atlanta Tower: Week of November 10-17

November 13, 2017

Structure Footings: We have reached several major milestones in construction of the Piedmont Atlanta Hospital Tower, most recently the basement level footings of the structure,...
  • Building Update for Piedmont Atlanta Tower: Week of November 3-10

Building Update for Piedmont Atlanta Tower: Week of November 3-10

November 3, 2017

Collier Road Work: In conjunction with a plan developed with the city of Atlanta, work will take place to install a water line under Collier...
  • Building Update for Piedmont Atlanta Tower: Week of November 3-10

Building Update for Piedmont Atlanta Tower: Week of October 27 – November 3

October 28, 2017

Collier Road Work: In conjunction with a plan developed with the city of Atlanta, work will take place to install a water line under Collier...
  • Building Update for Piedmont Atlanta Tower: Week of October 20-27

Building Update for Piedmont Atlanta Tower: Week of October 20-27

October 20, 2017

Hydrovacing Across Collier Road: In preparation of a water line installation, crews will be hydrovacing under Collier Road, a process that will better prevent damage...
  • Progress from October 13-20

Building Update for Piedmont Atlanta Tower: Week of October 13-20

October 16, 2017

Potholing Across Collier Road: A water line will be installed across Collier Road, near the front areas of the buildings located at 2 Collier Road...
  • The foundation is currently being constructed at the new Piedmont Medical Building

Building Update for Piedmont Atlanta Tower: Week of October 6-13

October 6, 2017

Potholing Across Collier Road: As we prepare for a water line installation across Collier Road, crews will hydrovac under the road, a process that will...

Building Update for Piedmont Atlanta Tower: Week of September 29 – October 6

September 29, 2017

September 29-October 6 First slabs: We reached a major milestone in construction as we poured the first concrete slabs of what will be the very...

Building Update for Piedmont Atlanta Tower: Week of September 22-29

September 22, 2017

September 22-29 Peachtree Road Lane Closings: This project is currently underway to connect underground utilities across Peachtree Road. Overnight work (9 p.m. to 4:30 a.m.) will...

Building Update for Piedmont Atlanta Tower: Week of September 15-22

September 15, 2017

Peachtree Road Lane Closings: Due to constraints presented by Tropical Storm Irma, construction on Peachtree Road has been postponed. This work will now take place...

Building Update for Piedmont Atlanta Tower: Week of September 8-15

September 8, 2017

Peachtree Road Lane Closings: Due to constraints presented by Hurricane Irma, construction on Peachtree Road has been postponed until Wednesday, September 13. Hurricane Irma: As...
  • The Pit as of September 1, 2017

Building Update for Piedmont Atlanta Tower: Week of September 1-8

September 5, 2017

Peachtree Road Lane Closings: Water line installation will now take place over a 6-day period from Thursday, September 7 through Tuesday, September 12. Work will...
  • Major Site Excavation

Building Update for Piedmont Atlanta Tower: Week of August 25 – September 1

August 25, 2017

Peachtree Road Lane Closings: To coordinate with other activities and roadwork planned on Peachtree Road, there has been a change to the schedule for the...

Building Update for Piedmont Atlanta Tower: Week of August 18-25

August 21, 2017

Peachtree Road Lane Closings: Crews will begin work on Wednesday, August 18, along Peachtree Road cutting asphalt to install water tie-ins that will connect to...
  • Site Excavation

Building Update for Piedmont Atlanta Tower: Week of August 11-18

August 11, 2017

(UPDATE) Peachtree Road Lane Closings: Crews will begin work on Wednesday, August 18, along Peachtree Road cutting asphalt to install water tie-ins that will connect...
  • The Pit

Building Update for Piedmont Atlanta Tower: Week of August 4-11

August 5, 2017

Tower Cranes: Tower cranes are currently being erected in the fenced-off construction area. All three cranes will be erected by the end of September. The...
  • Site cranes

Building Update for Piedmont Atlanta Tower: Week of July 28-August 4

July 30, 2017

Tower Cranes: Tower cranes are currently being erected in the fenced-off construction area. All three cranes will be erected by the end of September. The...
  • july-21-28

Building Update for Piedmont Atlanta Tower: Week of July 21-28

July 21, 2017

Tower Cranes: Tower cranes are currently being erected in the fenced-off construction area. All three cranes will be erected by the end of September. Noise...
  • The pit for the new Piedmont Hospital

Building Update for Piedmont Atlanta Tower: Week of July 14-28

July 14, 2017

First Tower Crane Erected: Tower cranes are currently being erected in the fenced-off construction area. All three cranes will be erected by the end of...
  • The pit for the new Piedmont Hospital

Building Update for Piedmont Atlanta Tower: Week of July 7-14

July 7, 2017

First Tower Crane Erected: Tower cranes are currently being erected in the fenced-off construction area. A total of three cranes will be erected by the...

Building Update for Piedmont Atlanta Tower: Week of June 30 – July 7

July 1, 2017

Drilling Materials: Drilling continues this week near the East Tower and the former 1-Center area. Minimal impact is expected on the hospital and the surrounding...
  • Footings

Building Update for Piedmont Atlanta Tower: Week of June 23-30

June 23, 2017

Drilling for Central Energy Plant: Crews will begin drilling caissons in the area that will house Piedmont Atlanta Tower’s central energy plant. Minimal impact is...
  • Working in the pit

Building Update for Piedmont Atlanta Tower: Week of June 16-23

June 19, 2017

Recycling Demolished Materials: As we demolish certain structures around the hospital, crews are exploring options to haul materials to recycling plants. From the Sheffield Building...